New home timeline


  • October 24th 2016 Saw the Carolina Place model for the first time





  • November 3rd 2016 Listed our Condo
  • May 25th Closed on our condo
  • June 8th 2017 Got a pre approval with NVR
  • June 9th 2017 Chose our lot priced out options and signed our contract and put $5k down.
  • June 16th 2017 Started our loan process
  • June 23rd 2017 Met with T.A.C Tile to choose design center options
  • June 24th 2017 Met with Guardian to choose security system options and wiring. On the same day we met with our Ryan Homes rep to finalize our structural choices.
  • July 6th 2017 We were approved for our loan!
  • July 9th 2017 Paid our $20k good faith money
  • July 31st 2017 scheduled our meeting with out PM for 8/25 we are scheduled to break ground on 9/4
  • August 24th 2017 Our Pre Build meeting was moved up a day but they did give us 3 days notice. New estimated break date is 9/6/2017


  • Comments

    Popular posts from this blog

    New Chapter

    This weekend kick started a new chapter in our lives. We are building a home! Originally we were going to go with Quality Built Homes (QBH) the Brentwood model. This was our dream home everything about it was perfect…or so we thought. Nothing against them at all they were professional, helpful and patient. However, we could not look past the commute my husband would have to make (1hr 15mins one way not including traffic) we are a close family and enjoy our time together. Also, we were not 100% sold on a propane tank heating system nothing wrong with it just not a fit for us. Soooooo we went with Carolina Place with Ryan homes. Check in soon for the next blog with the details.